Brazosport ISD – School Bond Project Scheduling

Clute Texas

The Brazosport Independent School District passed a school bond for $175 million for numerous new facilities and renovations and repairs to existing facilities.  The first major project in the program was a new prototype elementary school.

Hired after the Bond passage and commencement of design work, LAN assisted the district with the review of the schedule established by the architect and provided a complete assessment of the project status and recommended a target opening date.

LAN reviewed the status of the design drawings, investigated status of coordination with authorities having jurisdictions, approval milestone requirements, district self-performed work and numerous other factors that determine the schedule.  Ultimately, LAN prepared a summary report and master schedule for the project.

At a glance

Reviewed CMaR and Architect contract requirements for performance requirements

Clarified scope of District self-performed activities

Identified requirements for approval by Authorities Having Jurisdiction

Confirmed internal District approval milestones

Verified requirements for District startup

Prepared alternates for project phasing

Reviewed the status of construction document completion

Developed risk matrix for various scheduling scenarios

Completed project schedule for use by project team

Features

A third-party opinion of schedule

Conducted interview with District leadership

Work completed on compressed schedule

The district adopted recommended schedule

Services

K-12 Bond Program Management

Client

Brazosport Independent School District