Brazosport ISD – School Bond Project Scheduling
Clute Texas
The Brazosport Independent School District passed a school bond for $175 million for numerous new facilities and renovations and repairs to existing facilities. The first major project in the program was a new prototype elementary school.
Hired after the Bond passage and commencement of design work, LAN assisted the district with the review of the schedule established by the architect and provided a complete assessment of the project status and recommended a target opening date.
LAN reviewed the status of the design drawings, investigated status of coordination with authorities having jurisdictions, approval milestone requirements, district self-performed work and numerous other factors that determine the schedule. Ultimately, LAN prepared a summary report and master schedule for the project.
At a glance
Reviewed CMaR and Architect contract requirements for performance requirements
Clarified scope of District self-performed activities
Identified requirements for approval by Authorities Having Jurisdiction
Confirmed internal District approval milestones
Verified requirements for District startup
Prepared alternates for project phasing
Reviewed the status of construction document completion
Developed risk matrix for various scheduling scenarios
Completed project schedule for use by project team
Features
A third-party opinion of schedule
Conducted interview with District leadership
Work completed on compressed schedule
The district adopted recommended schedule
Services
K-12 Bond Program Management
Client
Brazosport Independent School District