By Mackrena Ramos, PE, Melissa Mack, PE, PMP, and Greg Henry, PE
Houston’s large-diameter water transmission projects demonstrate how early planning and coordination can help teams anticipate construction challenges, manage risk, and keep complex programs moving as conditions change through a developed corridor.
Across the country, public agencies are investing to expand capacity, replace aging infrastructure, improve reliability, and prepare essential systems for future growth. The scale of these investments and the desire to limit individual project size (within local contractor bonding capacities) requires phasing large capital programs into multiple projects that may take years or decades to plan, design, and construct.
Construction becomes especially challenging at that scale. Project scopes and schedules need to remain fluid enough to enable existing systems to remain in operation. Changes on one project can affect work elsewhere. On large-diameter pipeline programs, various jurisdictional requirements, construction access, tunneling constraints, long-lead materials, environmental considerations, and the sequence in which segments become operational can further influence decisions made during design.
In recent years, the City of Houston has utilized several such programs to extend its surface water transmission system across the city. The Surface Water Transmission Program (SWTP) and related regional transmission efforts provide an example of managing construction challenges at a large scale. Since 1985, these programs have guided the planning, design, construction, assessment, and maintenance of more than 300 miles of large-diameter transmission infrastructure ranging from 24 to 120 inches, involving multiple contracts, operating requirements, and regional partners.
LAN served as program manager and technical advisor for these programs, where recurring construction challenges highlighted important considerations for planning and delivering future large-diameter pipeline programs.
Address Construction Requirements Before Work Reaches the Field
Large capital programs involve multiple design firms and contractors working on separate projects. Advancing that work concurrently increases the importance of consistent design guidelines and construction requirements to ensure consistency.
On the Northeast Transmission Line (NETL), pipe diameters reached up to 120 inches. Steel pipe was selected at the program level to standardize key design elements and future maintenance requirements across thirteen contracts. The City and LAN also developed criteria for utility separation, backfill, loading over vulnerable utilities, haul routes, and equipment and material staging.
Across Houston’s large-diameter transmission work in urban neighborhoods, the key was to identify how work would be implemented within limited rights-of-way, existing and ongoing development, and access and staging constraints during design. On major pipeline and tunnel projects, those considerations can also influence shaft locations and construction methods, material and equipment access, excavated-material removal, and impacts to surrounding properties.
The series of projects comprising the Southwest Pump Station Secondary Refill Line presented another set of constraints as the 72-inch pipeline was constructed through established neighborhoods in Midtown and Montrose. The project included approximately 1,500 tree evaluations, including mature live oaks over 100 years old. The team adjusted the alignment where needed, coordinated tree protection measures, and used tunneling in sensitive areas. Construction planning also had to account for historic neighborhoods and long-established institutions.
Construction of the Southwest Pump Station Secondary Refill Line through established neighborhoods required careful planning around mature trees, existing development, access, utilities, and limited construction space.
Environmental requirements influenced other projects. Surveys were performed for bald eagles and nesting birds, while wetlands and other sensitive areas were fenced-off or tunneled to avoid disturbance.
Tunneling required additional technical planning. Detailed shaft and tunnel design accounted for groundwater control, mixed soil conditions, shoring, and crossings beneath major transportation corridors. The trenchless design affects construction access and worker safety and must avoid oversimplifying design and construction at the expense of long-term operations and maintenance.
Surface water transmission line construction in Houston has required specialized approaches to tunneling, groundwater control, shaft design, and work within constrained urban corridors.
Match procurement and packaging to the work
Materials, equipment, and labor are at the heart of every construction project. As pipelines increase in diameter, so does the scarcity of readily available materials, machinery, and experienced contractors. Proper procurement anticipates construction needs. Competitive sealed proposals were used on several complex projects, allowing the City to consider contractor qualifications and experience in addition to price. Contractor workshops also helped communicate technical requirements and constructability considerations and accept contractor feedback before bidding. This strategy helped mitigate specific challenges before bid, reducing risk and subsequent bid costs and change orders.
On long-duration pipeline programs, how work is packaged and sequenced can affect construction schedules, access to specialized contractors, commissioning, phasing around long-lead materials, and costs. Considering those issues and program schedule can help prevent rework by ensuring each package properly adjoins adjacent packages. These timely procurement decisions can optimize the program costs by purchasing materials during favorable market conditions.
“On a complex capital program, the decisions made before construction often determine how many options remain when challenges reach the field and conditions begin to change.”
– Greg Henry, PE
Account for Dependencies Between Contracts
A capital program may be divided into individual contracts with distinct construction requirements and different contractors, but the completed projects must ultimately operate as an integrated system.
NETL was constructed through 13 contracts that progressed on different schedules. Some intermediate segments were completed before adjoining sections were ready, requiring the project team to determine how to manage those pipelines until the full transmission line could be commissioned. As program manager, LAN recommended that the City of Houston’s Drinking Water Operations group be maintain the newly constructed lines until they were placed in service by filling the pipelines with water, periodically testing the water quality, and chlorinating as needed when levels dipped below the regulated standards.
Another program, the Southeast Transmission Line (SETL), provides an additional example. As technical advisor, LAN supported the City of Houston and seven other co-participant cities to evaluate four alternatives for connecting a proposed 54-inch line to an existing 96-inch prestressed concrete cylinder pipe. The alternatives required either a complete shutdown of the transmission main or significant pressure reductions, neither of which adequately met water demands during the tie-in.
LAN ultimately recommended to extend SETL approximately 1.5 additional miles to the Southeast Water Purification Plant. The solution required additional engineering, real estate acquisition, cost, and schedule but avoided the construction risks of tapping the aging 96-inch line. Furthermore, the extension to the plant allowed the new system to operate independently. This minimized the immediate construction impact and also provided permanent redundancy for the aging portion of the system, allowing for better maintenance and longer shut-down flexibility in the future.
The example illustrates why the shortest construction solution is not always the best program solution.
Establish Clear Coordination and Decision-Making
Large regional infrastructure efforts can involve multiple agencies, designers, construction managers, and contractors. Defining responsibilities and decision-making authority early helps teams respond when issues arise and reduces the risk of coordination delays.
SETL involves eight participating entities, with Houston serving as managing co-participant and LAN as technical advisor. Multiple design and construction management firms participated under the City and LAN’s guidance. A roles-and-responsibilities matrix, recurring progress meetings, coordinated design reviews, field visits, and co-participant discussions provided structure for resolving issues and coordinating decisions.
The same need for visibility continues during construction. On NETL, monthly construction updates, including drone video, kept the City’s internal teams and four water authority partners informed across the 13 contracts. Because the partner authorities had approval authority for major change orders and claims, maintaining visibility into construction progress helped support timely decisions.
Ongoing field coordination and construction reporting help keep project teams and stakeholders informed as work advances, supporting timely evaluation of changes and other issues.
Maintain a systemwide perspective
Individual projects have separate scopes, budgets, and schedules. With those constraints, the designer and contractor must be held accountable to serving the City and its constituents long-term by supporting the performance and operation of the larger system.
Houston’s experience shows how decisions made before and during construction connect across a program. Technical criteria were coordinated across projects, sequencing and commissioning incorporated input from Drinking Water Operations, contractors provided input and were procured based on their experience, and regional partners remained involved in decisions affecting their systems and investments.
For public agencies delivering large-diameter pipeline programs, establishing consistent technical requirements, planning construction access and sequencing, coordinating procurement, defining decision-making processes, and involving operations throughout delivery can reduce risk while helping each project contribute to the long-term performance of the larger system.
Mackrena Ramos, PE, has 27 years of experience specializing in large-scale water transmission, distribution programs, and capital improvement planning. Her leadership on the City of Houston’s Surface Water Transmission Program includes managing design teams, budgets, schedules, and stakeholder coordination for complex urban infrastructure projects.
Greg Henry, PE, is a professional engineer with 25 years of experience in large-diameter water and wastewater pipeline assessment, rehabilitation, design, and construction oversight. His experience includes trenchless methods, tunnel design, emergency repairs, condition assessments, and shutdown planning.
Melissa Mack, PE, PMP, is a LAN principal-in-charge with nearly three decades of engineering and project management experience specializing in hydraulic and transient modeling, master planning, and water infrastructure design.
Related Services
Explore Water → Planning, design and construction services for water supply, transmission and distribution infrastructure.
More Insights