Engineering Solutions for Complex Regional Water Transmission
Experience That Delivers Measurable Results
Expanding regional water transmission infrastructure requires balancing system capacity, reliability, construction costs and integration with existing facilities. Addressing these challenges demands engineering expertise informed by experience with large-diameter pipelines and complex operating water systems.
LAN brings direct experience with Tarrant Regional Water District (TRWD), extensive large-diameter pipeline design capabilities and specialized technical expertise to support the delivery of major regional water infrastructure.
Meet Our North Texas Pipeline Leadership Team
-

Philip Wheat, PE
Project Manager
Philip brings more than 19 years of experience in large-diameter pipeline engineering and program delivery. His work includes transmission pipelines up to 120 inches in diameter and management of water infrastructure programs exceeding $250 million, with an emphasis on technical coordination and project execution.
-

Reyna Johnson, PE
Deputy Project Manager
Reyna has more than 11 years of experience supporting large-diameter water transmission projects, including pipelines up to 120 inches in diameter. Her experience includes leading a 72-inch pipeline alignment study and coordinating technical design considerations to support constructability and project delivery.
-

Justin Reeves, PE
Principal in Charge
With more than 20 years of experience, Justin provides leadership in major water transmission projects, including direct experience with TRWD's IPL Section 15-1 and Richland-Chambers Pipeline Lowering. His background includes large-diameter pipeline design, project management and coordination of complex water infrastructure improvements.
Specialized Expertise for Complex Water Systems
-

Greg Henry, PE
Rehabilitation & Shutdown Planning
With more than 27 years of experience, Greg has led shutdown planning for critical water transmission infrastructure and developed rehabilitation plans for pipelines ranging from 24 to 96 inches in diameter.
-

Jim Gower, PE
Valve Design
Experience developing custom large-diameter valve solutions, including valves exceeding 108 inches and design specifications for 60- and 72-inch raw water transmission systems.
-

Jeremy Nakashima, PE
Pump Station Tie-ins
Experience integrating new piping and valves into existing pump stations, including temporary 60-inch valve systems designed to maintain operations during construction.
-

Bob Card, PE
Fittings & Tie-ins
Designed specialized fittings for TRWD's 90-inch Richland-Chambers Pipeline Lowering and engineered connections accommodating more than 1 million pounds of elbow thrust.
Engineering Complex Tunnels and Vertical Shafts
Managing Subsurface Constraints and Construction Risk
Large-diameter water transmission pipelines frequently encounter highways, waterways, utilities and developed corridors where conventional open-cut construction may not be practical.
Successful tunnel design requires evaluating more than the crossing itself. Ground conditions, shaft locations, excavation methods, groundwater, adjacent infrastructure and construction access can influence alignment selection, cost and project risk.
LAN's approach incorporates these considerations during design to help clients evaluate feasible construction methods and identify potential challenges before construction begins.
Our experience includes large-diameter tunnels, deep vertical shafts and crossings beneath major transportation corridors.
Long, Large-Diameter Tunnel Crossings
Long tunnel crossings require coordination of excavation methods, ground support, pipe installation and construction sequencing.
LAN's US-59 tunnel design experience includes a 1,050-foot crossing with a 126-inch steel liner and an open-face tunnel boring approach. The design included consideration of challenging subsurface conditions and ground treatment requirements.
Deep Vertical Shafts
Deep shafts introduce specialized design and construction considerations, including excavation support, groundwater management, access and the transition between vertical and horizontal pipeline segments.
On Dallas Water Utilities' Cedar Crest Water Line Relocation, LAN designed 100-foot-deep secant pile shafts associated with a 385-foot, 108-inch hard-rock tunnel carrying an 84-inch steel waterline.
Tunneling in Developed Corridors
Long tunnel crossings require coordination of excavation methods, ground support, pipe installation and construction sequencing.
LAN's US-59 tunnel design experience includes a 1,050-foot crossing with a 126-inch steel liner and an open-face tunnel boring approach. The design included consideration of challenging subsurface conditions and ground treatment requirements.