Lake Ralph Hall Pipeline Named ENR's 2026 Texas Project of the Year

The Lake Ralph Hall Pipeline, Balancing Reservoir and Delivery Point has been named the Texas Project of the Year in Engineering News-Record’s (ENR) Texas & Southeast 2026 Best Projects competition. The project also received ENR's regional Best Project award in the Water/Environment category, recognizing its engineering excellence, innovative construction methods and contributions to North Texas' long-term water supply. The project team was recognized at ENR's Texas & Louisiana Best Projects Awards luncheon Oct. 28 in Houston.

Developed by the Upper Trinity Regional Water District (UTRWD), the $254 million project includes 32 miles of large-diameter water transmission pipeline, a balancing reservoir and a regional delivery point. Lockwood, Andrews & Newnam, Inc. (LAN) served as owner adviser for design and inspection, working alongside construction manager-at-risk Garney and design firms Jacobs and Black & Veatch.

The Lake Ralph Hall Pipeline is designed to transport up to 54 million gallons of raw water per day from Lake Ralph Hall, one of Texas' newest reservoirs, to communities across North Texas. With the region's population projected to grow approximately 42% over the next 25 years, the project represents a significant investment in securing a reliable, long-term water supply.

"Lake Ralph Hall demonstrates what can be accomplished through early collaboration, thoughtful planning and a shared commitment to delivering critical infrastructure," said Justin Reeves, PE, LAN vice president. "The coordination required to deliver a project of this magnitude was significant, but the result is a water supply system that will serve North Texas communities for generations. We're proud to have supported UTRWD and the entire project team in this achievement."

The project's scale and complexity required extensive coordination among multiple engineering firms, contractors and stakeholders. Construction included 22 hand-mined tunnels totaling nearly 4,000 linear feet beneath roads, railroads and creeks, as well as a 1,600-foot tunnel beneath the South Sulphur River. The team also navigated challenging soil conditions, deep excavations and a critical connection to an existing 72-inch transmission main within a 72-hour shutdown window.

Using a construction manager-at-risk delivery approach, the team divided the work into 16 bid packages, allowing procurement to advance alongside design. Strategic timing of steel purchases generated more than $10 million in savings, contributing to approximately $25 million in total savings for UTRWD.

The recognition highlights the collective efforts of UTRWD, LAN and the entire project team in delivering critical water infrastructure to support North Texas' continued growth.